Subpart Q Process Unit Information for Units Monitored by CEMS
Note: The Cal e-GGRT help system includes general instruction on using the California GHG reporting tool. However, the help system may not explain differences between California and U.S. EPA reporting requirements. Please refer to the ARB reporting website for California-specific reporting requirements and additional help.


This page provides step-by-step instructions on how to enter and edit Subpart Q Iron and Steel Production process unit information for units that are monitored by CEMS.

Under Subpart Q, "process units" may include any of the following:

  • Taconite indurating furnace
  • Basic oxygen process furnace
  • Non-recovery coke oven battery
  • Sinter process
  • Electric arc furnace (EAF)
  • Decarburization vessel
  • Direct reduction furnace

Step 1: Add a process unit

To add a process unit that is monitored by CEMS, find the UNIT SUMMARY (Units Monitored by CEMS) table on the Subpart Overview page and click the link titled "ADD a CEMS Unit." When you report emissions information later you will have the opportunity to indicate or identify if a CEMS Monitoring Location (CML) is monitoring multiple units that may share a common stack.

To later edit information identifying a process unit, click the edit icon or the Name/ID link located in the first column of the table.

To delete a process unit, click the delete icon or red “x” located in the last column of the table.

Click image to expand

Step 2: Enter required information for the process unit

For each process unit monitored by CEMS at your facility, Subpart Q requires you to report the following information:

  • A unique name or identifier for the process unit, plus optional description of the unit
  • The type of process unit, selected from the following:
    • Taconite indurating furnace
    • Basic oxygen process furnace
    • Non-recovery coke oven battery
    • Sinter process
    • Electric arc furnace (EAF)
    • Decarburization vessel
    • Direct reduction furnace

When you are finished entering all required information for the process unit, click SAVE.

Click image to expand

Step 3: Repeat Steps 1-2

Repeat Steps 1-2 until all process units monitored by CEMS have been added for your facility.

#Back to Top

See Also

Screen Errors
Using Cal e-GGRT to Prepare Your Subpart Q Report
Subpart Q Process Unit Information for Units NOT Monitored by CEMS
Subpart Q Process Unit Information for Units Monitored by CEMS
Subpart Q Coke Pushing Operations Information
Subpart Q Flares Information
Subpart Q Emissions Information for Units NOT Monitored by CEMS
Subpart Q Emissions Information for Units Monitored by CEMS
Subpart Q Emissions Information for Coke Pushing Operations
Subpart Q Emissions Information for Flares
Subpart Validation Report

This web site is maintained by a contractor to the California Air Resources Board (RY2015.R.03)