Q85. Is the use of Subpart C tiers required after 2010 and is it acceptable to use the best available monitoring provisions under Subpart A beyond 2010?

Disclaimer This information is intended to provide general and administrative information about 40 CFR Part 98. It does not represent legal advice. This information does not have legally binding effect or expressly or implicitly create, expand, or limit any legal rights, obligations, responsibilities, expectations, or benefits in regard to any person. Facility owners or operators and suppliers are responsible for determining how they would be affected by the requirements of 40 CFR Part 98.

Q85. Is the use of Subpart C tiers required after 2010 and is it acceptable to use the best available monitoring provisions under Subpart A beyond 2010?

A85. Yes, the use of Subpart C Tiers is required after 2010. The use of best available monitoring methods as described in Subpart A may not be extended beyond the end of 2010 except for units subject to subpart P (Hydrogen Production), subpart X (Petrochemical Production), or subpart Y (Petroleum Refineries).  Note that there may be subpart specific BAMM requirements not included in subpart A-. Note, however, that this timing does not apply to subpart-specific BAMM requirements-. (See §98.3(d)(2)(iii) and §98.3(j).)

Updated on Feb 14, 2013 10:10

Adaptavist Theme Builder Powered by Atlassian Confluence